Possibility of application of backfill methods with cementing fill in ore body Borska reka

Mogućnost primene metoda otkopavanja sa zapunjavanjem otkopanog prostora stvrdnjavajućim zasipom u uslovima rudnog tela Borska reka

  • Dejan Petrović University of Belgrade – Technical faculty in Bor
  • Vitomir Milić University of Belgrade – Technical faculty in Bor
  • Igor Svrkota University of Belgrade – Technical faculty in Bor
  • Saša Stojadinović University of Belgrade – Technical faculty in Bor http://orcid.org/0000-0002-0286-2881
  • Miodrag Denić University of Belgrade – Technical faculty in Bor
Keywords: 'Borska Reka' orebody; mining methods; stope backfill

Abstract

The orebody 'Borska Reka' is dipping at great depth and above the ore body there are parts of the settlement and traffic facilities essential for the region. Geological conditions in which ore body occurs, low copper content in the ore and objects on the surface in addition makes the process of adopting the optimum mining method of this ore relative. In addition to the block caving and sublevel method with ore and overburden rocks collapses should be considered and sublevel and open stope mining methods with backfilling the excavated area. Possibility of application of backfill methods with cementing fill for 'Borska Reka' orebody condition are presented in this paper.

References

ATLAS COPCO (2007) Mining methods in underground mining - Atlas Copco Rock Drills AB. Stockholm: Atlas Copco, pp. 33-45.

MIHAJLOVIĆ, B., MILIĆEVIĆ, Ž. and SVRKOTA, I. (2008) Mining of Borska Reka ore body summit. In: Proceedings of 40th October conference on Mining and Metallugy, Sokobanja, October 2008. Bor: Mining and Metallurgy Institute Bor & University of Belgrade - Technical Faculty in Bor, pp.73-78.

MILIĆ, V., SVRKOTA, I. and PETROVIĆ D. (2011) Analysis of current situation, possibilities and perspective of underground mining in Jama Bor. In: Proceedings of 43th International October Conference on Mining and Metallurgy, Kladovo, October 2011, Bor: Mining and Metallurgy Institute Bor & University of Belgrade - Technical Faculty in Bor, pp.521-524.

MILIĆEVIĆ, Ž. (2011) Underground mining methods of ore deposits (in Serbian). Bor: RDS Group, pp.327-348.

MINING AND METALLURGY INSTITUTE BOR (2010) Additional mining project for a permanent suspension of work in the ore bodies "Tilva Roš" and "P 2 A" and operational safety and collective protection of the Bor mine. Bor: Mining and metallurgy institute, pp.98-99.

PETROVIĆ, D. et al. (2012) "Borska Reka" orebody, the future of the exploitation in Bor mine. Underground mining engineering, 21, pp.83-88.
Published
2015-12-31
How to Cite
Petrović, D., Milić, V., Svrkota, I., Stojadinović, S., & Denić, M. (2015). Possibility of application of backfill methods with cementing fill in ore body Borska reka. Podzemni Radovi, (27), 1-10. https://doi.org/10.5937/podrad1527001P